MIL-C-81360(AS)
Test Periods - The test may be run continuously or intermittently. Any
4.5.2
period of operation shall be of sufficient duration to permit the equipment temperature to
stabilize. Periodically, the equipment shall be turned on and off several times and put
through its various phases of operation.
4.5.3
Performance Check - At approximately 8-hour intervals during the test,
a limited performance check shall be made. The performance check proposed by the con-
tractor shall be subject to approval by the procuring activity.
Test Data - The contractor shall keep a daily record of the performance
4.5.4
of the equipment, making particular note of any deficiencies or failures. In the event of
part failures, the defective part shall be replaced and the operation resumed for the balance
of the test period. A record shall be kept of all failures throughout the test. This record
shall indicate the following:
(1) Part type number
(2) Circuit reference symbol number
(3) Part function
(4) Name of manufacturer
(5) Nature of failure
(6) Number of hours which the part operated prior to failure
Failure Report - In the event of a failure, the government inspector
4.5.4.1
shall be notified immediately. A report shall be submitted to the procuring activity upon
completion of the test. In this report, the contractor shall propose suitable and adequate
design or material corrections for all failures which occurred. The procuring activity will
review such proposals and determine whether they are acceptable,
Reconditioning of Life Test Samples - Equipment which has been sub-
4.5.5
jected to the life test shall be reconditioned as follows:
(1) On completion of the life test, the equipment shall be reworked by the
contractor by replacing all "wear" items. The "wear" items shall
be determined by agreement between the contractor and the procuring
activity.
(2) After reworking, the contractor shall resubmit the equipment for
acceptance.
Test Procedures - The procedures used for conducting preproduction
4.6
tests, acceptance tests and life tests shall be prepared by the contractor and submitted to
the procuring activity for review and approval. The right is reserved by the procuring
activity or the government inspector to modify the tests or require any additional tests
deemed necessary to determine compliance with the requirements of this specification or
the contract. Specification MIL-T-18303 shall be used as a guide for preparation of test
procedures. When approved test procedures are available from previous contracts such
12