4.4
Acceptance Tests - The contractor shall furnish all samples and shall
be responsible for accomplishing the acceptance tests. All inspection and testing shall be
under the supervision of the government inspector. Contractors not having testing facilities
satisfactory to the procuring activity shall engage the service of a commercial testing lab-
oratory acceptable to the procuring activity, The contractor shall furnish test reports
showing quantitative results for all acceptance tests. Such reports shall be signed by an
authorized representative of the contractor or laboratory, as applicable. Acceptance or
approval of material during the course of manufacture shall not be construed as a guarantee
of the acceptance of the finished product. Acceptance tests shall consist of the following:
(1) Individual tests
(2) Sampling tests
(3) Reliability assurance tests
(4) Special tests
Individual Tests - Each equipment submitted for acceptance shall be
4.4.1
subjected to the individual tests. These tests shall be adequate to determine compliance
with the requirements of material, workmanship, operational adequacy and reliability, As
a minimum, each equipment accepted shall have passed the following tests:
(1) Examination of product
(2) Operational test
(3) Manufacturing run in test
Examination of Product - Each equipment shall be examined carefully to
4.4.1.1
determine that the material and workmanship requirements have been met.
Operational Test - Each equipment shall be operated long enough to
4.4.1.2
permit the equipment temperature to stabilize and to check sufficient characteristics and
record adequate data to assure satisfactory equipment operation.
4.4.1.3
Manufacturing Run In Test - Each equipment shall be operated under the
conditions specified herein for a period of 6 hours without failure. A failure shall be de-
fined as anything which causes malfunctioning of the equipment. Only those adjustments
will be permitted which can be made by using such controls and adjustments that are
accessible to the operator during the normal use of the equipment,
Ambient room
Temperature
Ambient room
Humidity
Any selected frequency within
Vibration
the range of 20 to 30 Hz
(excluding resonant points) and
a minimum amplitude of + g's